Tuesday, March 5, 2013

Forest Heights: Construction Begins On Skilled Trades Centre

Construction is underway on a new skilled trades centre at Forest Heights Community School in Chester Basin. Director of Operations with the local school board, Steve Prest, says Rikjak Project Inc. of Lunenburg is on-site and started their work a little over a week ago. Prest says he's impressed with the work that's done to date.



Construction was pegged to last until the end of May, but Prest adds, the contractor has set a completion date for May 1st. The project cost is roughly $283,000 and is considered the number one priority by the school board's operations department.