MODL awards landfill closure contract to Dartmouth group


A Dartmouth company has been awarded the contract for final landfill closure at the Lunenburg Regional Community Recycling Center. The Municipality of the District of Lunenburg selected ABL Environmental for the design and engineering services of phase two and three at a cost of almost $194,000 including HST. The project had a budget of $200,000. Mayor Don Downe says it's nice to see it remained under budget. The Municipality received five submissions for the project, with every proposal coming from either Halifax or Dartmouth. During phases two and three of the Landfill Remediation project, permanent caps will be put over the landfill cells at the LRCRC to protect the environment.